Lesson 8.2: Capstone: a complete migration plan
The capstone brings the whole course together. Each team receives a scenario and writes the migration plan a real project would start with, proves one part of it on a training installation, and presents it. The trainer reviews it with the rubric below. The rubric is the trainer's own course material, not an official certification.
At a glance
| Course | Migrating to Exponential |
| Module | Module 8: Leaving Exponential, and the capstone |
| Duration | 90 minutes (10 presenting, 55 team work, 25 presentations and review) |
| Level | Advanced |
| Audience | Mixed teams: an administrator, a developer and, if possible, a project manager |
| Prerequisites | Modules 1 to 7, or at least modules 1 to 3 and the module of the team's scenario |
Learning objectives
After this lesson, learners can:
- choose and justify a migration path for a realistic site;
- write a plan that covers every section of the common checklist;
- prove one risky part of the plan on a training installation;
- present the plan and answer questions on rollback and addresses.
Trainer's notes
How to present it
- Brief (5 minutes). Hand out the scenarios (below), one per team. Each team writes its plan in a shared document using the headings in the exercise.
- Rules (5 minutes). Every claim in the plan cites a page of the documentation. Where the documentation does not say something (a duration, a vendor detail), the plan says "to be measured" or "to be checked", never a guess. The proof runs only on the team's training installation.
- Team work (55 minutes). Walk between the teams. Ask each team the two questions that matter most: "What do you
do if the final import fails?" and "Where does
/old/addresslead on day one?" - Presentations (20 minutes). Five minutes per team; the other teams ask one question each.
- Review (5 minutes). Score with the rubric; give each team one strength and one improvement.
Scenarios
- The old intranet. A 4.7 site of the legacy kernel on PHP 5 and MySQL with
latin1tables, two siteaccesses, three own extensions, 9 000 objects in one language, the database cluster handler, 150 users (some withmysqlhashes). Target: Exponential 6. - The 5.x portal. A community 2014.11 site with the dual-kernel stack: Twig front end, one REST bundle for an app, image variations in YAML, two siteaccesses matched by host. Target: Exponential 6.
- The Ibexa campaign site. Ibexa OSS 4.6 with Netgen Layouts, RichText, 20 Page Builder landing pages and a team that knows Twig. Target: decide between Nexus and Exponential 6, then plan.
- The WordPress magazine. 3 000 posts in two languages (a translation plugin), a page builder plugin on 40 pages,
an SEO plugin, 12 000 attachments,
/%category%/%postname%/permalinks, 30 editors. Target: Exponential 6.
Common questions
Can we pick a different scenario? Yes, if it is a real kind of site and the team can cite the documentation for it; for example the static HTML guide or another system guide of the migration hub.
How detailed must the plan be? Every heading filled; the depth goes into the riskiest part.
Pitfalls
- Plans without a rollback. The rubric gives no points for a plan that cannot go back.
- Proofs on a public demonstration installation or any shared site. Proofs run only on the team's own training installation.
- Invented numbers. "The import takes three hours" without a rehearsal is a guess; write "to be measured in rehearsal 1".
Hands-on exercise
In teams, with the migration hub and the chapter of your scenario open.
- Write the heading Path and the guide the decision table of the migration hub gives, with the reason.
- Write Inventory: the items of checklist section 1 and, for your scenario, the extra checks of its chapter (14.3, 15.4, 16.4 or the system guide).
- Write Scope and owners: the table of checklist section 2 with a decision and an owner per row.
- Write Mapping: a mapping table for the two most important content types, plus users and passwords.
- Write Tools: the tool or script for each part (lesson 3.1's table).
- Write Addresses: five rows of the redirect table, including the hardest one.
- Write Rehearsals and tests: how many, what is measured, which tests from checklist section 7.
- Write Cut-over and rollback: the runbook in ten lines, triggers, decider, decision window, dumps kept.
- Choose the riskiest part of the plan and prove it on your training installation: for example a dry-run import
with xrowextract, a redirecting alias or wildcard tested with
curl, the preflight queries, or an INI translation checked withexp:ini get. Note the commands and the result. - Prepare a five-minute presentation: path, the riskiest part and its proof, rollback.
Expected result
- A plan with all nine headings filled, every claim citing a documentation page, unknowns marked "to be measured" or "to be checked".
- A proof with commands and their output from the team's training installation.
- A presentation within five minutes.
The trainer scores each plan with this rubric (three levels per criterion, maximum 18 points):
| Criterion | 0: not yet | 1: partly | 2: fully |
|---|---|---|---|
| Path | none or unjustified | named, weak reason | named with the decision table and the generation or source |
| Inventory and scope | missing parts | most parts, some owners | every checklist item, every row with an owner |
| Mapping | no table | some fields | both types complete, users and passwords decided |
| Tools | none named | named without reason | each part with its tool or script and why |
| Addresses | none | some rows | five rows incl. query strings or patterns, test method |
| Rehearsal and tests | none | one run, few tests | two or more runs, counts, samples, redirects |
| Cut-over and rollback | missing | runbook or rollback | both, with triggers, decider and dumps |
| Proof | none | attempted | run, with commands and result |
| Sources | none | some | every claim cited; no invented figures |
Quiz
- What is the first thing a team does with its scenario?
- Which three things must the rollback section contain?
- Where may a team run its proof? A. On a public demonstration installation B. On any shared site C. Only on its own training installation D. On production
- How does a plan treat a duration the documentation does not give?
- True or false: a team that completes the capstone holds an official Exponential certification.
Answers
- Find the path with the decision table of the migration hub.
- Triggers, who decides, and the decision window; plus the dumps kept (checklist, section 9).
- C.
- As "to be measured" in a rehearsal (chapter 14.15).
- False. The rubric is the trainer's own course material; it is not an official certification; the partner program's certifications are separate (Certifications).
Further reading
- The common migration checklist: the frame of every plan.
- Migrating to and from Exponential: the hub and every guide.
- Quizzes and practical tasks: how to build fair assessments and rubrics.
Related pages
- Module 8: Leaving Exponential, and the capstone
- Migrating to Exponential: course overview
- Trainers: start here
- Free documentation: this page is free to copy, translate and improve under the GNU FDL 1.3.
Become an Exponential Partner
Partners share their information, provide funding, contribute back and develop the products with us, and that is how Exponential grows. A partner website and dashboard are planned for mid-2027: please become a partner today to speed up our growth rate and land new features faster.