Lesson 1.4: The run sheet

Write the minute-by-minute run sheet of a workshop day, who does what, when, which help page and exercise, the checkpoint of each block, the cut items, and the end-of-day clean-up. 35 minutes.

Download as PDF

Address: https://doc.exponential.earth/exphelp/viewer/help/trainers/workshops/module-01-planning-a-workshop/the-run-sheet.md

On this page

Lesson 1.4: The run sheet

An agenda says what the day covers. A run sheet says who does what at each minute, how you know a block worked, and what goes if time runs short. Trainers and helpers work from the same sheet.

At a glance

CourseWorkshops and bootcamps
ModuleModule 1: Planning a workshop
Duration35 minutes (10 presenting, 25 exercise)
LevelIntermediate
AudienceTrainers
PrerequisitesLesson 1.1; one agenda of Module 2

Learning objectives

After this lesson, learners can:

  • turn an agenda into a run sheet with times, owners, materials and checkpoints;
  • mark a cut item per block;
  • plan the helpers' tasks;
  • include the end-of-day clean-up.

Trainer's notes

How to present it

  1. Show the columns (5 minutes): time, block, owner (trainer or helper), material (help page, lesson), checkpoint (the visible result), cut item.

  2. Show an example row (5 minutes):

    TimeBlockOwnerMaterialCheckpointCut item
    10:30Create and publish an articleTrainer; helpers walk the roomCreating your first articleEvery learner's article at version 2The language step

Common questions

Who keeps time? One helper, with a quiet signal at five minutes before the end of each block.

What if a block runs over? Apply its cut item, not the next block's exercise.

Pitfalls

  • No checkpoints. Without them, you only know at the end that the morning did not work.
  • Forgetting clean-up. It is part of the day.

Hands-on exercise

  1. Take the Editors day agenda.
  2. Write the run sheet for the morning: at least five rows with every column.
  3. Name the timekeeper and the helper tasks.
  4. Add the last row: clean-up (stop servers or remove accounts, collect feedback slips).

Expected result

  • A morning run sheet of five or more rows, every row with a checkpoint and a cut item.
  • Helper tasks and the clean-up row.

Quiz

  1. Name the six columns of a run sheet.
  2. What is a checkpoint?
  3. A block runs over. What do you cut?
  4. Why is clean-up on the run sheet?
Answers
  1. Time, block, owner, material, checkpoint, cut item.
  2. The visible result that shows the block worked (for example, an article at version 2).
  3. That block's planned cut item.
  4. So it is not forgotten: stopped servers, removed accounts, collected feedback.

Further reading

Become an Exponential Partner

Partners share their information, provide funding, contribute back and develop the products with us, and that is how Exponential grows. A partner website and dashboard are planned for mid-2027: please become a partner today to speed up our growth rate and land new features faster.

Something wrong on this page? Report an error

Documentation license

This documentation is free documentation, licensed under the GNU Free Documentation License 1.3 or later.

Exponential Copyright © 1998-2026 Exponential Foundation and 7x