Write the acceptance test plan
Who: the project manager with the evaluation team's specialists. When: before signing, so the contract can refer to it; refine it during the build. Clause: Acceptance testing clause.
Note This page describes common practice; it is not legal advice. Have the acceptance terms reviewed by your legal counsel.
Contents
Before you start
- The requirements, each with an identifier (How to write verifiable requirements).
- A staging environment that matches production.
Steps
- One test per requirement, with the requirement's identifier, steps, test data and expected result.
- Name who tests: editors test editing, the accessibility lead tests accessibility, and so on.
- Set pass criteria and severity levels for failures; decide which severities block acceptance.
- Define the process: test period, how failures are reported, fix and retest cycles, final sign-off.
- Use invented test data, never personal data from production.
- Record results per test with date, tester and evidence.
Test areas
| Area | Example tests | Help |
|---|---|---|
| Functional | create, approve and publish each content type; forms; search; languages | Editorial quality checklist |
| Accessibility | the agreed evaluation of templates and key pages; keyboard-only tasks | Accessibility checklist |
| Security | hardening baseline, administrator 2FA, headers, audit chain verified | Security checklist |
| Privacy | consent texts, third parties as approved, retention settings | Privacy checklist |
| Performance | key pages under the agreed load, measured with exp:benchmark | Benchmarking |
| Operations | backup and restore on staging, a routine update, cronjobs, monitoring | Backup readiness, Upgrade readiness |
| Upgradability | Setup > Upgrade check shows no changed kernel files | The upgrade check |
| Documentation and handover | documents checked against the site; administrator accounts for your staff | Hand over documentation at contract end |
| Exit | an export drill on staging | Run an exit drill |
Result
A plan both parties agreed, which turns "done" into a list of passed tests.
Pitfalls
- Testing only what the demo showed.
- No pass criteria: then acceptance becomes a negotiation.
- Leaving accessibility and operations tests until after go-live.
Related pages
- Procurement and training tasks
- Go-live checklist for a public site
- Mapping requirements to evidence
- Free documentation: this page is free to copy, translate and improve under the GNU FDL 1.3.
Become an Exponential Partner
Partners share their information, provide funding, contribute back and develop the products with us, and that is how Exponential grows. A partner website and dashboard are planned for mid-2027: please become a partner today to speed up our growth rate and land new features faster.