Write the evaluation scoring sheet
Who: the project manager with the evaluation team. When: before the tender is published; many procurement rules require the criteria and weights to be published with it. Templates: Scoring sheet template and Weighting criteria.
Note This page describes common practice; it is not legal advice. Follow your organization's procurement rules.
Contents
Before you start
- Requirements final, split into mandatory (pass or fail) and scored (Requirements).
- Evaluation team named (Build an evaluation team).
Steps
List mandatory requirements as pass/fail gates: a bid that fails one is out.
Group scored criteria, for example: solution fit, accessibility, security, privacy, operations and support, training, exit and lock-in, project plan, price over the term.
Set weights that reflect your priorities; they add up to 100.
Define a score scale with words, so scorers agree on what a number means:
Score Meaning 0 not addressed 1 addressed, no evidence 2 partly met, some evidence 3 met, with evidence 4 met, with strong evidence and a credible plan Name the evidence for each criterion: a demo step, a document, a proof-of-concept task, a reference answer. For product facts, the panel can check the bidder's claims against the standards pages (Check a vendor's accessibility claims).
Price over the term: score the total cost of ownership model, not the first year (Total cost of ownership).
Plan moderation: scorers score alone, then agree in a meeting; record the reasons for each final score.
Example
Criterion Weight Evidence Lead scorer
Solution fit 25 demo script steps 1-8, PoC tasks 1-3 editorial lead
Accessibility 15 test report method, demo with keyboard accessibility lead
Security 10 hardening plan, patching commitment security officer
Privacy 10 processing plan, third-party list DPO
Operations and support 10 SLA answers, staffing, upgrade hours IT specialist
Training 5 course outline, material rights training coordinator
Exit and lock-in 5 exit plan, export test offer project manager
Price over <n> years 20 TCO model filled in project manager
Total 100The weights are an example; choose your own.
Result
A sheet published with the tender, which every scorer applies the same way.
Pitfalls
- Price weighted so high that quality cannot change the result.
- Criteria without evidence: they get scored on the quality of the prose.
- Changing weights after bids are opened.
Related pages
- Procurement and training tasks
- Evaluation checklist template
- Red flags and pitfalls
- Free documentation: this page is free to copy, translate and improve under the GNU FDL 1.3.
Become an Exponential Partner
Partners share their information, provide funding, contribute back and develop the products with us, and that is how Exponential grows. A partner website and dashboard are planned for mid-2027: please become a partner today to speed up our growth rate and land new features faster.